You Can’t Commission What You Can’t Document
- Gregg Shupe
- Aug 25
- 3 min read
Most cleanroom and technical facility projects focus heavily on layout, utilities, and equipment. All critical. But what slows down a project after construction isn’t the hardware. It’s the paperwork.

Teams often wait until turnover to define what documentation they need to start operations. By then, they’re behind. SOPs aren’t approved. Validation protocols are still being written. Teams haven’t reviewed the environmental monitoring plans, causing weeks of preventable delay.
This doesn’t need to happen. Documentation planning should start in preconstruction, not at the end.
What We Mean by Documentation Planning
Documentation isn’t just SOPs and logbooks. It’s everything your project needs to move from construction to compliant, audit-ready operations.
Commercial and Project Documentation
Design and Construction Specifications
System and Process Documentation
GxP and Quality Documentation
Monitoring and Compliance Records
These categories need to be scoped, assigned, and scheduled during preconstruction so they align with your turnover and operational readiness goals. If they’re missing, the delay is built in.
Why Preconstruction Documentation Planning Matters
Documentation systems affect validation, training, turnover, and regulatory approvals. When they’re not aligned with the project plan, everyone loses time. These challenges show up across industries and follow the same pattern.
Documentation Failures in Pharma, Semiconductor, and AI Data Centers
Pharmaceuticals
An ISPE-aligned case study showed that biotech teams with heavy CQV documentation requirements fell behind schedule because they failed to integrate document development early. Teams assembled protocols during handover, left logbooks incomplete, and extended validation for weeks longer than expected (ISPE).
Semiconductors
Samsung delayed the opening of its Taylor, Texas, fab until 2026 due to a lack of customers. Public sources cite permitting and market conditions, but across the industry, cleanroom certification delays are common. Fabs need structured airflow testing data, cleanroom logs, and tool installation documentation to proceed. When that plan isn’t defined early, even fully built facilities stall at the finish line (Holland & Hart, Evertiq).
AI Data Centers
A report from Exponent noted that over $60 billion in data center projects in the U.S. are delayed or blocked, many due to permitting and ESG reporting failures. Clients now expect structured documentation for energy use, uptime, humidity control, and sustainability metrics. If teams fail to scope those records during preconstruction, they scramble to retrofit systems under pressure. (Exponent, EkkoSense).
This pattern extends beyond one sector. In every case, the absence of a documentation structure creates bottlenecks when the project should be moving forward.
Where Projects Go Sideways
SOPs are still in draft after mechanical completion
Cleanroom testing is done, but supporting documentation is missing
ESG reports are expected, but there’s no data governance in place
Batch records don’t align with equipment design
Training can’t start because the documents aren’t finalized
What Good Looks Like
At Hygenix, we work with capital project teams early to define what documentation needs to be created, who owns it, and when it needs to be delivered.
Aligning documentation planning with turnover and CQV milestones
Mapping controlled document needs to system readiness
Supporting SOP and protocol frameworks
Coordinating with QA, IT, operations, and compliance teams
Reviewing vendor documentation, expectations, and format alignment
This planning eliminates rework, prevents compliance delays, and keeps your startup on track.
Start Here
Identify which departments will own the documentation
Set deadlines for controlled document readiness based on turnover
Align document creation with CQV and validation timelines
Ensure your vendors understand what records they must deliver
Engage your quality and operations teams early, not after construction
You Don’t Need More Paper. You Need a Plan.
Technical environments like cleanrooms, fabs, and AI data centers don’t fall behind because of poor design. They fell behind because they treated documentation as a post-construction task.
If your project is moving forward without a documentation plan, you’re already behind schedule. Let’s fix that.